Monday, December 27, 2010
December 16-18, 2010
Dec 16, 2010 Moved electrical panel started to excavate for foundation.
Dec 17, 2010 Finished excavation, dug footings.
Dec 18, 2010 finished digging footings by hand.
Dec 17, 2010 Finished excavation, dug footings.
Dec 18, 2010 finished digging footings by hand.
Wednesday, December 22, 2010
December 1, 2010
Chris, John and Clint removed the stone wall and started to dig for the electrical lines.
The are the main line to the house, line to the well, line to the out buildings. We had to did into our memories to know which line went where.
The photos show a tangled web of lines by the basement door.
The are the main line to the house, line to the well, line to the out buildings. We had to did into our memories to know which line went where.
The photos show a tangled web of lines by the basement door.
November 29, 2010
Met with Kathy about the cabinets and make many decisions regarding the look and function of them.
I did not know that there were so many other decisions for the cabinets other than door fronts and wood and stain choices.
I did not know that there were so many other decisions for the cabinets other than door fronts and wood and stain choices.
November 22, 2010
Kitchen Designer, Kathy Euston came out to house for final measurements for the cabinets.
Contractor, Chris Hooper met here with engineer and electrician.
Contractor, Chris Hooper met here with engineer and electrician.
Tuesday, December 21, 2010
November 16, 2010
First day of construction, or destruction.
Removal of lower deck roof. Weather was 50*
Day 2 November 17,2010
Removal of siding from garage and laundry room walls. Weather light rain 38*
Removal of lower deck roof. Weather was 50*
Day 2 November 17,2010
Removal of siding from garage and laundry room walls. Weather light rain 38*
Subscribe to:
Posts (Atom)